A two-storey skeleton house with a total area of 108 m2 is distinguished by an unusual appearance and non-standard planning solutions
![Raise Sails!](/userfiles/56/12554_4.webp)
![Raise Sails!](/userfiles/56/12554_5.webp)
![Raise Sails!](/userfiles/56/12554_7.webp)
![Raise Sails!](/userfiles/56/12554_8.webp)
![Raise Sails!](/userfiles/56/12554_10.webp)
This miniature house, which reminds its outlines, not the exotic bird, severly on the emerald lawn, is not the ship, rushing on all sails "on the green stroy of the sea," is located in one of the country's country villages. The appearance of the construction intrigues: it is distinguished by a non-standard approach to the distribution of volumes. The building is expanding as the height increases, "throwing out" into the space balconies, similar to the captain's bridges, and the roof of a complex shape, similar to the wind-filled sail.
When building a residential building on the summer site, it is often necessary to deal with the need to save space. However, this should not affect the quality of housing conditions. Today we want to offer you one of the options for solving such a difficult task.
The cities began the country house designed so that it combines several functions. The wholesale floor was planned to place a garage and utility premises, and on the uppermost zone, designed to accommodate a family of three. It was assumed that the messages between these two levels would not be, so for each of them organized their input. However, the idea of relying part of the ground ground area under the sauna, the water treatment area (shower) and a rest room, which was made subsequently appeared. Nevertheless, not to lose the precious space, the inner staircase between the floors did not arrange, but left separate inputs. Of particular inconvenience, this host does not deliver, because the house is mainly in the warm season.
Chalet Variations
The design of the house was largely influenced by the architecture of the chalet, which enjoy greatly popular. Highlights of this type are very attracted, for example, a steady stone base, which extends a lighter wooden part. Another advantage of their dignity of the oops of the roof, protecting against rain and snow not only adjacent to the building with the territory, but also balconies and terraces. However, these well-known techniques have found unusual applications here. It led the original form of the structure: the roof gained a complex shape with a plurality of fades, and the traditional terrace was replaced by spacious balconies, as if soaring over the ground. Supplemented by a contrast combination of colors and textures in the finishing of facades, as well as characteristic windows, these details work on the creation of a solid image of the house.
Step by step...
Despite the miniature of the construction, it came to its construction with special care. Before eating the foundation, on the territory they carried out drainage work for removal of ground and melt waters. The base of the house is made of monolithic reinforced concrete. Plots of the walls below the soil level are provided with a vertical waterproofing - protective composition of the penetrating action "Calmatron" (Russia) - both outside and from the inside. The walls of the residential premises in the baseway were insulated with a polystyrene foam of 30mm, and for heat insulation, extruded polystyrene foam 100mm was used. The top floor is a light and economical wooden frame design. Punching insulating material for the walls was used by mineral wool ISOVER (Finland) with a thickness of 300mm. It is protected by film vapor barrier, and overall insulation from pergamine. Ventilation gap - 40mm.Floors shares the overlap of reinforced concrete slabs, which is additionally supported by a diagonally located metal beam (partly it affected the lowest room configuration). The protrusions of these plates form balconies: one of them is located in the living room area of the first floor, and the second forms a peculiar porch at the entrance to the house.
Assue Queue, overlapping the top floor is made of wood, like the rafting construction of the roof. The ceiling and part of the roof slopes included in the interior of the premises, along with walls are insulated with ISOVER mineral wool (300mm). This concern for thermal insulation is relevant not only in winter (it allows you to maintain heat in the house), but also hot summer (during the day the room is not heated).
Heat in the house
In the cold season, the house is heated with electricity. Splocks are equipped with electric heat floors, and wall-mounted electrical radiators are installed on the first floor. Electricity is used for hot water: on both floors, 100 liters each boilers are provided. Moreover, if the water ends in the socket level boiler, the water heating system of the first floor is connected. Comfort in the house also provides a system forced ventilation: all this equipment is in the attic room above the ceiling of the first floor.
Since the life support of the building is almost completely dependent on electricity, in the case of electricity interruptions in the municipal network in the house there is a diesel generator. It is located in a special garage compartment.
Solar symphony
The house creates a very cozy, easy atmosphere. The main mood in the residential premises of the first floor sets a wooden finish. Walls and ceilings everywhere, including in the bathroom, are truncated, and a pine board is laid on the floor. A transparent water-based lacquer, which is covered with all surfaces, retains natural light tree tone, and thanks to this, the interior is like sunlight. The alternation of light and dark fragments of a wooden trim having natural color transitions forms a kind of rhythmic pattern.The objects of the situation are also selected in the light natural range: it is wooden dining room furniture, an alberta Salotti sofa (Italy) in the living room. The facade of the Euromobil Kitchen Front (Italy) of a saturated orange tone plays the role of a bright color accent that introduces the dynamics in the interior of the public zone.
Relax zone
A completely different setting in the recreation area of the basement. Wooden wallpapers are replaced by wallpaper, plasterboard ceiling and ceramic tile, which is lined with floor. The main tone milk-beige- creates an atmosphere of a comfortable SPA-salon, which is pleasant to relax after the shower and sauna. Comfortable recreation is a comfortable soft sofa; There is a small kitchen where you can cook tea or soft drinks (a built-in refrigerator is installed under the table top).
Some official rest of the rest room compensates for the cheerful and very warm decoration of the water treatment zone. Here, as in the representative part of the first floor, there is a sunny-orange color - in the floor cladding with a stoneward, as well as in bright decorative inserts with floral pattern - on the walls.
Plan of the ground floor
1. Room rest
2. Tambour
3. Sanusel
4. Garage
5. Sauna
6. Water procedures zone (shower)
1. Bedroom
2. Sanusel
3. Wardrobe
4. Hallway
5. Children's
6. Kitchen
7. Living-Dining Room
Technical data
Total house area 108m2
Designs
Building type: frame
Foundation: Monolithic reinforced concrete belt type, depth - 1.4 m, vertical waterproofing - protective composition of the penetrating action "Calmatron", horizontal waterproofing - waterproofing membrane
Walls: Central Floor-monolithic reinforced concrete, insulation - polystyrene (30mm); First floor-wooden frame, insulation- mineral wool isover (300mm), vaporizoation - vapor insulation membrane, windproofing, pergamine, ventilation gap - 40mm, casing- lining
Overlapping: Socular Floor-concrete plates; First floor- Wooden, vapor barrier film, insulation- mineral wool ISOVER (300mm)
Roof: scope, insulated, constructional construction, wooden rafters, thermal insulation - mineral wash ISOVER (300mm), waterproofing - waterproofing membrane; Roofing metal profiled sheet
Windows: plastic with single-chamber windows REHAU (Germany)
Life support systems
Power supply: municipal network, diesel generator
Water supply: centralized
Hot water supply: two electrical boilers (volume - 100l)
Heating: Electric Heating Floors, Electric Retail
Sewerage: Septic
Interior decoration
Walls: Pine Wallpaper, Wallpaper, Ceramic Tile
Ceilings: Pine Lining, Plasterboard
Floors: Pine board, porcelain stoneware
Furniture: Alberta Salotti, Euromobil, in Sanuzlakh- Jacob Delafon (France)
Plumbing: IDO (Finland)
The enlarged calculation of the cost * home improvement with a total area of 108m2, similar to the submitted
Name of works | Number of | price, rub. | Cost, rub. |
---|---|---|---|
Preparatory and Foundation Works | |||
Takes up axes, layout, development and recess | 60m3. | 630. | 37 800. |
Trench Drainage Drainage Drainage | set | - | 29 000 |
Sand base device, rubble | 10m3 | 410. | 4100. |
Device of the foundations of ribbon reinforced concrete | 30m3 | 4200. | 126,000 |
Device of foundation plates of reinforced concrete | 14m3 | 4000. | 56,000 |
Waterproofing horizontal and lateral | 140m2. | 380. | 53 200. |
Other works | set | - | 27 500. |
TOTAL | 333 600. | ||
Applied materials on the section | |||
Concrete heavy | 44m3. | 3900. | 171 600. |
Gravel crushed stone, sand | 10m3 | - | 13 000 |
Waterproofing | 140m2. | - | 36 400. |
Materials for drainage device (pipes, well) | set | - | 95,000 |
Armature, Formwork Shields and Other Materials | set | - | 89,000 |
TOTAL | 405,000 | ||
Walls, partitions, overlap, roofing | |||
Device of reinforced concrete walls | 37m3 | 4600. | 170 200. |
Installation of metal structures | set | - | 10 800. |
Laying plates of floors, balconies | 56m2. | 340. | 19 040. |
Assembling frame walls and partitions | 130m2 | - | 135,000 |
Assembling roof elements with crate device | 110m2. | 690. | 75 900. |
Isolation of walls, overlap and coatings insulation | 290m2. | 90. | 26 100. |
Hydro and vaporizoation device | 290m2. | 60. | 17 400. |
Metal coating device | 110m2. | 590. | 64 900. |
Installing window blocks | set | - | 19 500. |
Device terraces, porch | set | - | 58,000 |
Swinging sinks | set | - | 29 200. |
Other works | set | - | 129 000 |
TOTAL | 755 040. | ||
Applied materials on the section | |||
Concrete heavy | 37m3 | 3900. | 144 300. |
Rental of steel, steel hydrogen, fittings | set | - | 19 400. |
Plates of overlapping | 56m2. | 1600. | 89 600. |
Sawn timber | 16m3. | 6900. | 110 400. |
Steam, wind and waterproof films | 290m2. | - | 10 100. |
Mineralovate insulation | 290m2. | - | 34 500. |
Metal profiled sheet, Dobornye elements | 110m2. | - | 95 700. |
Window blocks with double-glazed windows, entrance doors | set | - | 106,000 |
Other materials | set | - | 370 000 |
TOTAL | 980,000 | ||
Engineering systems | |||
Installation of wastewater treatment system | set | - | 33 800. |
Electrical and plumbing work | set | - | 379,000 |
TOTAL | 412 800. | ||
Applied materials on the section | |||
Local sewage system | set | - | 107 800. |
Stove-Kamenka (Finland) | set | - | 19 800. |
Plumbing and electrical equipment | set | - | 695,000 |
TOTAL | 822 600. | ||
FINISHING WORK | |||
Painting, facing, assembly and carpentry work (including facade) | set | - | 912,000 |
TOTAL | 912,000 | ||
Applied materials on the section | |||
Lining, porcelain stoneware, board floor, plasterboard, door blocks, facing stone, decorative elements, varnishes, paints, dry mixes and other materials | set | - | 1 830 000 |
TOTAL | 1 830 000 | ||
* The calculation was performed on the averaged rates of construction companies Moskva, without taking into account the coefficients. |